Port Fairy pool update

TECHNICAL investigations are continuing at the Port Fairy pool and gym facility.


With improved access to the Southcombe Park precinct following the Port Fairy Folk Festival, on-site inspections were expected to begin earlier this week.

These inspections will assess the condition of the building, as well as plant and pool infrastructure – including structural elements and the extent of mould contamination.

Moyne Shire mayor Cr Jordan Lockett said the findings would help form council’s next steps regarding the future of the facility.

“This is an important step that will help us better understand the facility’s condition, and provide cost estimates on rectification, maintenance and renewal, and components,” Cr Lockett said.

“We will continue to keep the community informed as the investigation progresses.”

It is believed contractors have been on site since Monday, preparing safe access to the roof.

They will also disconnect selected solar panels to allow access to required inspection points.

During the week structural engineers will undertake a detailed assessment of building structural elements including portal frames, purlins and roof bracing connections.

They will also inspect the condition of the building’s west wall and the concrete concourse around the pool shell.

Dates are yet to be confirmed for the assessment of the pool shell, plant and ancillary services.

The final report is expected to be considered at the May 26 council meeting.